A63 Update

National Highways Notification - A63 South Cave to North Ferriby

Friday 23 May 2025

'Most of the snagging activity is completed. Most of the work on the eastbound is complete. We do still have a few activities on the westbound side to complete which will take next week to complete but barring any major faults being identified in the final tests (we certainly don’t expect any) work will complete at the end of next week, so there should be no traffic management extending into June'.

 

The Transport Management plan as per my previous email still applies, i.e.

26th – Bank holiday embargo, no work planned

27th – Lane one closures, plus closure of Melton west bound entry slip road

28th – Full closure west bound

29th – Lane closures

30th – Lane closures”